Completed
Ayala Malls Vermosa
Client:
Ayala Land Inc. / MDC
Package:
Supply & Installation of 4 x 2500 kVA Mitsubishi Genset
Date of Contract:
October
2019
Completed
Packhouse 3
Client:
Eagle Cement Corp.
Package:
Supply & Delivery of 1 x 1361 kVA Mitsubishi Genset
Date of Contract:
November
2019
Completed
Vista Mall Gen. Trias
Package:
Supply & Installation of 2 x 2000 kVA Mitsubishi Genset w/ Synchronizing Panel
Date of Contract:
February
2018
Completed
Vista Mall Tanza
Package:
Supply & Installation of 2 x 2000 kVA Mitsubishi Genset w/ Synchronizing Panel
Date of Contract:
February
2018
Completed
Vista Mall Ilo-Ilo Ph. 2
Package:
Supply & Installation of 1 x 2000 kVA Mitsubishi Genset
Date of Contract:
August
2018
Completed
Vista Mall Malolos
Package:
Supply & Installation of 3 x 1750 kVA Mitsubishi Genset w/ Synchronizing Panel
Date of Contract:
August
2018
Completed
Vista Mall Naga Ph. 2
Package:
Supply & Installation of 1 x 2000 kVA Mitsubishi Genset
Date of Contract:
August
2018
Completed
UST Hospital Expansion Bldg.
Client:
University of Sto. Tomas
Package:
Supply & Installation of 2 x 2000 kVA Mitsubishi Genset w/ Synchronizing Panel
Date of Contract:
August
2018
Completed
Vista Mall Davao
Package:
Supply & Installation of 2 x 2000 kVA Mitsubishi Genset w/ Synchronizing Panel
Date of Contract:
August
2018